Size
29 Acres
-
Contract Value
$4.4 Million
-
Completion
April 2021
-
Duration
1.5 Years
Problem Solved
This job had an aggressive schedule, a lot of rock, and we started in the dead of winter.
We were able to crush the rock to be utilized on site for access through the winter, and we lime-stabilized the dirt fill to allow us to continue forward and achieve compaction and deliver the site on time.
Scope of Work
Completed the sitework for construction of the new Messick’s Equipment headquarters and warehouse. This project required us to move approximately 97,00 cubic yards of dirt, as well as installation of 6,200 linear feet of storm, sewer, and water utilities. There was also 35,000 square yards of paving required for the site.
During construction, we excavated roughly 39,000 cubic yards of rock. Most of this rock was able to be crushed on-site and repurposed back into the project.
Customer Contact: Matt Eshelman | meshelman@chnsite.com
More Projects
-
Old Trail Intermediate School
West Shore School District
-
156 W. Harrisburg Avenue
Catalyst Commercial Development
-
Easton Road Ballfields
Lower Saucon Township